B
Bill
I have created a project schedule by first listing all
the tasks then inserting the durations for each task.
The task type is Fixed Units for the entire schedule.
One of my tasks has a duration of 8 hours. While I
expected the resource to work on the task would have a
100% units, the best person available to do the task has
50% units availability. When I assigned this person with
50% units to the 8 hr task, I expected the duration to
change from 8 hours to 16 hours since the assigned
resource can only spend 50% of their time on the task.
However, the schedule still shows 8 hours duration even
though the assigned resource at 50% can only work four
hours on the task each day.
Why doesn't duration change on tasks when the assigned
resources have less than 100% units? Any advice will be
appreciated.
the tasks then inserting the durations for each task.
The task type is Fixed Units for the entire schedule.
One of my tasks has a duration of 8 hours. While I
expected the resource to work on the task would have a
100% units, the best person available to do the task has
50% units availability. When I assigned this person with
50% units to the 8 hr task, I expected the duration to
change from 8 hours to 16 hours since the assigned
resource can only spend 50% of their time on the task.
However, the schedule still shows 8 hours duration even
though the assigned resource at 50% can only work four
hours on the task each day.
Why doesn't duration change on tasks when the assigned
resources have less than 100% units? Any advice will be
appreciated.