Resource Availabilities not available in PWA

S

SHERLOCK1977

Dear Users,

I have the following problem. For some Resources the resource
availability in January 2006 is displayed as beeing 0 when rechecking
it in Ressource Center in PWA.

I have tried it with rescheduling the OLAP Cube period. It now is set
from 1.1 2006 to 31.12.2007. Cube is build correctly, however still for
some resources the availabilities in January cannot be seen. I receive
the following warning when entering the resource center.
"Warning: Availability data has not been published for one or more
resources
in the selected date range."

The resources where no availability for january 2006 can be seen are
every time the same.
The resource availability for all resources in MS Project Client is
displayed correctly when checking it in Resource Usage View.

Can anybody help me?

Rui
 
S

SHERLOCK1977

Hello Dave,

thank you for your informations. Unfortunately both ways didnt work.
First i rescheduled the OLAP to fetch availabilities from 1. Dec 2005
until 31.Dec 2007 with no result. Then I tried the second way, however
all resources are maintained correctly with Start NA and End NA.

Do you have any further suggestions which could help?

Rui
 
D

Dale Howard [MVP]

Rui --

My name is Dale, but you can call me Dave if you'd like. Please post this
question on the microsoft.public.project.server newsgroup and see if anybody
else can take a stab at your problem.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top