I am trying to use Resource Plans in Project 2007 but it doesn't seem
to be working. I would allot hours to my resources on the plan but
when i click on View Assignments or View Availability, it shows that i
have no assignments and that I still have 40 hours available. I
tested with 2 contacts and 2 different projects to double check.
Here's what I did:
1. Create a project plan with 1 task "Support".
2. Click on build team, and selected 2 resources (not sure if this is
necessary)
3. Save and Publish the project plan.
4. In PWA, selected the "Support" project and created a Resource Plan.
5. For Calculate Resource Utilization From: I selected "Project
Plan" ( also tried Resource Plan) and still didn't show decreased
availability
When I assign the resource to the task in the project plan, it shows
decreased availability, it is just in the resource plan, it is not
making any changes. Any help would be appreciated!
Thanks,
Linna
I am trying to use Resource Plans in Project 2007 but it doesn't seem
to be working. I would allot hours to my resources on the plan but
when i click on View Assignments or View Availability, it shows that i
have no assignments and that I still have 40 hours available. I
tested with 2 contacts and 2 different projects to double check.
Here's what I did:
1. Create a project plan with 1 task "Support".
2. Click on build team, and selected 2 resources (not sure if this is
necessary)
3. Save and Publish the project plan.
4. In PWA, selected the "Support" project and created a Resource Plan.
5. For Calculate Resource Utilization From: I selected "Project
Plan" ( also tried Resource Plan) and still didn't show decreased
availability
When I assign the resource to the task in the project plan, it shows
decreased availability, it is just in the resource plan, it is not
making any changes. Any help would be appreciated!