P
Proj_Admin
Hi,
My company holds weekly resource allocation and project prioritization
meetings utilizing Project Web Access 2003. Recently, there has been
increased pressure on project managers to figure out the following problem;
I have researched thoroughly but to no avail...
The resource availability, as represented in the bar graph, does not seem to
take into account completed tasks. We had a resource who recently submitted
a 100% complete update for a task [task A] in his timesheet. This task
update was accepted and saved. However, task A was not due to start or be
completed until April 10th. Now that task A is completed ahead of schedule,
my managers expected the resource availability view to account for this extra
time allotted to the resource. However, his availability for 4/10 still
shows him as working on task A, which has already been completed.
As you can imagine, this created quite a headache in the meeting, with
people questioning the integrity of Microsoft Project. I have faith that the
application is working correctly and that perhaps we are not utilizing the
correct feature settings. I'd love to be able to provide a resolution by our
next weekly meeting, on Monday. Any/all advice would be tremendously
appreciated!
Proj_Admin
My company holds weekly resource allocation and project prioritization
meetings utilizing Project Web Access 2003. Recently, there has been
increased pressure on project managers to figure out the following problem;
I have researched thoroughly but to no avail...
The resource availability, as represented in the bar graph, does not seem to
take into account completed tasks. We had a resource who recently submitted
a 100% complete update for a task [task A] in his timesheet. This task
update was accepted and saved. However, task A was not due to start or be
completed until April 10th. Now that task A is completed ahead of schedule,
my managers expected the resource availability view to account for this extra
time allotted to the resource. However, his availability for 4/10 still
shows him as working on task A, which has already been completed.
As you can imagine, this created quite a headache in the meeting, with
people questioning the integrity of Microsoft Project. I have faith that the
application is working correctly and that perhaps we are not utilizing the
correct feature settings. I'd love to be able to provide a resolution by our
next weekly meeting, on Monday. Any/all advice would be tremendously
appreciated!
Proj_Admin