Dkirkman
Hi I am trying to set a resources availability from 3/8/04 on to 50% availability. I went into the Resource sheet, selected the resource and updated the availability table by entering 3/8/04 in the Available From column, bypassing the Available To column and then entering 50% for the percentage. I click OK but the resoure is still being assigned the full amount of work hours for the tasks scheduled after 3/8/04. What am I doing wrong?