MS Proj Pro 2003 WITHOUT the Project Server.
I have a project file (.mpp) which I use as a resource pool and have a
number of projects using this file as the resource pool. When I make a new
resource available from a particular date ( a future date) or when I increase
or decrease availability on a resource from a particular date ( a future
date), the effect of that is not reflected after levelling. The altered
resource status takes effect only when I change the availability dates to the
current date or a past date. "How do I use a future date for resource
availablity and see the effect of that in my schedules?" I have not altered
the status date to any future date and I prefer not to tamper with the status
date because I use it for other purposes of rescheduling.
I have a project file (.mpp) which I use as a resource pool and have a
number of projects using this file as the resource pool. When I make a new
resource available from a particular date ( a future date) or when I increase
or decrease availability on a resource from a particular date ( a future
date), the effect of that is not reflected after levelling. The altered
resource status takes effect only when I change the availability dates to the
current date or a past date. "How do I use a future date for resource
availablity and see the effect of that in my schedules?" I have not altered
the status date to any future date and I prefer not to tamper with the status
date because I use it for other purposes of rescheduling.