K
kimberlydd3
The resources in my project gradually increase in the amount time they are
available to work on the project. So all the resources will be able to work
on the project 20% in March, 30% in April, and 100% in May-Dec. Here are the
steps I followed:
Added resources to Resource Sheet
For each resource went into the Resource Information dialog and adjusted the
Available to and From dates along with units to reflect the percentages
mentioned above.
Added tasks to the task sheet
Assigned resources to each task
Went to add work and I keep getting an overallocation message to reduce the
units.
I thought Project would automatically adjust the task duration based on the
resource availability I put in the Resource Information dialog but I guess I
am missing something. What is the best way to show that resources are
available 20% in March, 30% in April, 100% in May-Dec (there are no set hours
so I cant do it through the Working Calendar)? Lastly, is there a certain
way to assign the resources to the tasks so that project automatically adjust
for the varying resource availability from month to month?
I am using Project 2003
I appreciate any help you can provide.
Thanks.
available to work on the project. So all the resources will be able to work
on the project 20% in March, 30% in April, and 100% in May-Dec. Here are the
steps I followed:
Added resources to Resource Sheet
For each resource went into the Resource Information dialog and adjusted the
Available to and From dates along with units to reflect the percentages
mentioned above.
Added tasks to the task sheet
Assigned resources to each task
Went to add work and I keep getting an overallocation message to reduce the
units.
I thought Project would automatically adjust the task duration based on the
resource availability I put in the Resource Information dialog but I guess I
am missing something. What is the best way to show that resources are
available 20% in March, 30% in April, 100% in May-Dec (there are no set hours
so I cant do it through the Working Calendar)? Lastly, is there a certain
way to assign the resources to the tasks so that project automatically adjust
for the varying resource availability from month to month?
I am using Project 2003
I appreciate any help you can provide.
Thanks.