I'm trying to add a resource where the 'availability from' date is in the
future and the 'available to' date is indefinite. When i set the from date
in the resource information dialog box and hit OK it sets the 'available to'
date to what I entered in the 'available from' date field plus 1 day. Am I
adding resource dates incorrectly, do I need to set something in options to
change, or something/anything else? thanks in advance!
future and the 'available to' date is indefinite. When i set the from date
in the resource information dialog box and hit OK it sets the 'available to'
date to what I entered in the 'available from' date field plus 1 day. Am I
adding resource dates incorrectly, do I need to set something in options to
change, or something/anything else? thanks in advance!