J
JimC.
I have a specific resource and have made his working calendar so that Fridays
are Non-Working days for that one resource.
However when I assign that resource to tasks the project allows those tasks
to work on Fridays.
I am trying to ensure that when that resource is assigned that the tasks
that he is assigned to will not be able to work on Fridays.
This used to work fine with MS Project 2002, but when I upgraded to MS
Project 2003, SP1 this functionality stopped working.
Any ideas on what might have happened ??
are Non-Working days for that one resource.
However when I assign that resource to tasks the project allows those tasks
to work on Fridays.
I am trying to ensure that when that resource is assigned that the tasks
that he is assigned to will not be able to work on Fridays.
This used to work fine with MS Project 2002, but when I upgraded to MS
Project 2003, SP1 this functionality stopped working.
Any ideas on what might have happened ??