resource cost

M

mita

This is what i ant to know
lets say a resource AA cost me $100/hr. I am charging my client $150/hr.I
would like to have for all the tasks the coted value and the charged value .

how can it be one
 
G

Gérard Ducouret

Mita,
You can try the following:
I assume you entered Cost A and Cost B in each Resource Information dialog
(Tab Costs)
In the Resource Usage view, insert the Cost Rate Table field.
Make sure that every resource is set to Cost Rate A
Set Baseline1 : Tools / Tracking / Set Baseline... and select Baseline 1
In the Resource Usage view make sure that every resource is set to Cost rate
B
Set Baseline2 : Tools / Tracking / Set Baseline... and select Baseline 2
Then compare for each task the Basline1 Cost and Baseline2 Cost.
NB : you could add calculted field to calculate the margin

Hope this helps,

Gérard Ducouret
 