Hi,

I have custom Cost1 field setup. What I am looking for is to have cost
manualy entered in this field in TaskUsge or ResourceUsage view and have it
summed in COST1 for the assigned task. I guess it is how cost is getting
calculated for the task exept it will not be based on work (only manually
entered at this point). so far i had no success. To have Cost 1 to schow in
Task I had entered it at task level (not per assigned resource).


Thanks
 
J

John

YLE said:
Hi,

I have custom Cost1 field setup. What I am looking for is to have cost
manualy entered in this field in TaskUsge or ResourceUsage view and have it
summed in COST1 for the assigned task. I guess it is how cost is getting
calculated for the task exept it will not be based on work (only manually
entered at this point). so far i had no success. To have Cost 1 to schow in
Task I had entered it at task level (not per assigned resource).


Thanks

YLE,
Please see my response to Dann on his post "filtering tasks in resource
usage view" dated 2/3/06, in this newsgroup.

John