B
Baz-ITstrategist
Hi All
MS Project Prof 2003
I am trying to enter custom number or costs to resources in a task, using
the Task usage view, I am expecting the task Cost1 to roll up the resoucre
cost1's - as per following, but in my project the Task 1 does note get
calculated
(Cost 1)
- Task 1 $100
== Res1 $50
== Res2 $30
== Res3 $20
Thanks
Barry
MS Project Prof 2003
I am trying to enter custom number or costs to resources in a task, using
the Task usage view, I am expecting the task Cost1 to roll up the resoucre
cost1's - as per following, but in my project the Task 1 does note get
calculated
(Cost 1)
- Task 1 $100
== Res1 $50
== Res2 $30
== Res3 $20
Thanks
Barry