Resource costs

K

kazza_1963

How do I set up differing costs for a staff resource? E.g. a consultant
works three days per week at no charge for 15 days labour, thereafter there
is a per-day fee.
 
J

Jan De Messemaeker

Hi,

You can have different rates depending on the task
In Resource Information, Cost Pad, use the different (A:E) cost rate tables
Assign a cost rate table to tasks in the task usage view (Insert the Cost
Rate Table Column)
But different per day of the week is not possible, sorry.
HTH
 