T
Tony Chopp
What is the best way to handle a resource that is not
100% effective? Example: I have a 40 hour work week and I
have a task that is 16 hours of effort. If I assign Joe
he will can complete this task in 16 hours, but if I
assign Jeff it will take 32 hours because he is only 50%
as efficient at this task as Joe. The amount I get paid
for each of the 16 hours of effort is the same regardless
of which resource I use.
Thanks or you help.
Tony
100% effective? Example: I have a 40 hour work week and I
have a task that is 16 hours of effort. If I assign Joe
he will can complete this task in 16 hours, but if I
assign Jeff it will take 32 hours because he is only 50%
as efficient at this task as Joe. The amount I get paid
for each of the 16 hours of effort is the same regardless
of which resource I use.
Thanks or you help.
Tony