P
Paul
Hi all,
I'm working on my yearend planning for a development firm. I want to
evaluate the impacts of moving resource from one project to another on the
delivery dates when for example, 1 resource is working 100% on project A and
3 resources are working 50% of their time for the same project. Would like
to see the Gannt be modified.
Anyway to do this in Project?
Here's my situation:
- 5 Projects
- 50 ressources
- Ressources will move from one project to another depending the development
stage. When the project start there will be maybe 2 people working and at
the end 5 people.
- All projects require 3000 hours
I'm working on my yearend planning for a development firm. I want to
evaluate the impacts of moving resource from one project to another on the
delivery dates when for example, 1 resource is working 100% on project A and
3 resources are working 50% of their time for the same project. Would like
to see the Gannt be modified.
Anyway to do this in Project?
Here's my situation:
- 5 Projects
- 50 ressources
- Ressources will move from one project to another depending the development
stage. When the project start there will be maybe 2 people working and at
the end 5 people.
- All projects require 3000 hours