J
JimS
I am running Project Server 2003. I have 8 project schedules that have
resources that cross all projects. I have set the Project Priorities to
reflect the sequence that I want the projects to take. Within each project I
have assigned appropriate Task Priorities to reflect the actual work. I am
having a difficult time understanding how to resource all 8 project schedules
at the same time. Do I have to bring them into a "Master Project", then
resource level, and then save the resulting individual schedules?
resources that cross all projects. I have set the Project Priorities to
reflect the sequence that I want the projects to take. Within each project I
have assigned appropriate Task Priorities to reflect the actual work. I am
having a difficult time understanding how to resource all 8 project schedules
at the same time. Do I have to bring them into a "Master Project", then
resource level, and then save the resulting individual schedules?