hi Jonathan,
Microsoft Office Project 2003 levels overallocated resources by delaying and
splitting tasks, based on criteria you set. When you start the leveling
operation, Project checks each of the resources in turn. If a resource is
overallocated, Project searches for the tasks that are causing the
overallocation and identifies which of those tasks can be delayed. Project
does not delay tasks that have:
A constraint of Must Start On or Must Finish On.
A constraint of As Late As Possible, if this project is being scheduled from
the start date.
A constraint of As Soon As Possible, if this project is being scheduled from
the finish date.
A priority of 1000, meaning do not level.
An actual start date.
However, as long as the Leveling can create splits in remaining work check
box is selected, any remaining work can be split for leveling.
After determining which tasks can be delayed, Project picks the task to
delay based on its task dependencies, start date, priority, and constraints.
To review the changes leveling made to tasks, on the View menu, click More
Views. Click Leveling Gantt, and then click Apply. Review your tasks in the
Leveling Gantt view to see the results of leveling and to see how much delay
leveling has added to tasks.
Regards,