resource levelling

T

Tarmo

I try manage customer orders. Aim is to push received orders as late as
possible (but not later than dead-line) because then I can process incoming
urgent orders at once. Setting of activities are next: as late as possible,
fixed work, limitted resources, fixed minimum lags. But resource levelling
dont work. What should I do? I need something like automatic activities
movement in time scale.
 
J

Jan De Messemaeker

Hi,

I'm sorry to confirm that resource levelin can only postpone taks, so that
as late as possible tasks can never be leveled by Project.
 