Resource Loading not totalling correctly

B

Byron9261

I have a task with 2 resources and corresponding rates. When I added a new
resource to the task, the cost did not change. I double checked that I input
rates. The only thing I can think of is that I manually adjusted the hours
in the resource sheet. Does anyone have any suggestions?
-B
 
J

Jan De Messemaeker

Hi,

Don't forget that when the task is Effort Driven, adding a resource does not
result in more work; instead teh work on the task is divided between the
resources.
If you want an additional resource to result in additional work, go to Task
Information, Advanced Tab, check out Effort Driven.
HTH
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top