Z
Zed
Hi
Am struggling to get MSProject2003 to help me with effective resource
management. I have a couple of questions I'd be grateful for an answer to and
any helpful tips for resource management using MSP2003 would be appreciated
Is there a simple way to view on the resource usage screen (and report on)
just the activities by resource that should be taking place for this week?
I've tried filtering to date range but it doesn't appear to work properly.
Is there any way that non-working days can be shown as a different colour,
rather than white, on the resource usage screen?
Am struggling to get MSProject2003 to help me with effective resource
management. I have a couple of questions I'd be grateful for an answer to and
any helpful tips for resource management using MSP2003 would be appreciated
Is there a simple way to view on the resource usage screen (and report on)
just the activities by resource that should be taking place for this week?
I've tried filtering to date range but it doesn't appear to work properly.
Is there any way that non-working days can be shown as a different colour,
rather than white, on the resource usage screen?