So, I have multiple project plans shared to a single resource pool.

If I am in a specific project plan, how would I view just my own resources
in the resource "usage view" or "task view" while still sharing a resource
pool.
 
J

Jonathan Sofer

If you only have the one plan open, you should only see your one plan's
resource assignments.

Jonathan
 
J

JulieS

Hello Gianni,

I'm not sure I follow your question. When you say "view must my own
resources" are you asking to see only the resources assigned in your
specific project? If so, when you open your project file select the
option "Do not open other files" to view just resources and their
assignments in the project file you are opening.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
M

Mike Glen

Hi Gianni,

Welcome to this Microsoft Project newsgroup :)

Insert the Project column and filter for your project.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top