J
jidegold
I have drawn up an MSP schedule in which i have ten tasks that will all take
5 days in total-(start to start) so that the duration is 5 days, and i assign
a resource called "process analyst" to all 5, MSP gives me a resource usage
of 50 days for that resource, how do i tell MSP that it is the same resource
and that the activities are taking place in parralel?