J
Julie S
For cost estimating and scheduling, how can I tell Project that a resource
will only be used for a 12 hours over a 2 week time period. This resource
needs to be 100% dedicated to the task.
To better explain...
The resource above is a piece of equipment that cannot be moved around
easily. It will be dedicated to the task for the duration (2 weeks), but
will only be used 0 to 4 hours per day. How the time is divided on a daily
basis doesn't matter. Just the overall total time required (12 hrs) is all
that I need to capture for cost estimating. The resource needs to stay at
100%, we'll be able to tell if we're overallocating or not.
So for scheduling I need to say that this resource is being used for 2
weeks. But for cost estimating purposes, we're only charging the customer
for 12 hrs.
How can I do this?
Thanks,
Julie
will only be used for a 12 hours over a 2 week time period. This resource
needs to be 100% dedicated to the task.
To better explain...
The resource above is a piece of equipment that cannot be moved around
easily. It will be dedicated to the task for the duration (2 weeks), but
will only be used 0 to 4 hours per day. How the time is divided on a daily
basis doesn't matter. Just the overall total time required (12 hrs) is all
that I need to capture for cost estimating. The resource needs to stay at
100%, we'll be able to tell if we're overallocating or not.
So for scheduling I need to say that this resource is being used for 2
weeks. But for cost estimating purposes, we're only charging the customer
for 12 hrs.
How can I do this?
Thanks,
Julie