S
ST
Is there an efficient way to do the following?
At times the need arises where we need to change the the units that
resources are assigned to a task. With the task type set to 'fixed work',
changing the resource units for those that are assigned redistributes the
remaining work to the resources accordingly. This is great!
However, if we set the units for a resource to down to 0%, it does not
redistribute the remaining work. Is there an optimal way to do this because
if we enter zero units MS Project drops the remaining work for those
resource(s); we have to add back the remaining work at the task to get our
remaining work to what it was.
/Spiro Theopoulos.
At times the need arises where we need to change the the units that
resources are assigned to a task. With the task type set to 'fixed work',
changing the resource units for those that are assigned redistributes the
remaining work to the resources accordingly. This is great!
However, if we set the units for a resource to down to 0%, it does not
redistribute the remaining work. Is there an optimal way to do this because
if we enter zero units MS Project drops the remaining work for those
resource(s); we have to add back the remaining work at the task to get our
remaining work to what it was.
/Spiro Theopoulos.