C
Craig Newman
Dear All,
I'm having the following problem with Project 2000. I
have a task that is say 7 days, which I assign an
individual to work. The individual is 70% efficient with
the remaining 30% as overhead. To represent this
I have:
Actual Task: 7 days work with assign Individual[70%]
giving 10 days duration
To make sure that the individual overhead is not
allocated elsewhere I create a second task for the
duration period i.e.
Overhead: 10 days duration Individual[30%]
What I expect to see in the resource usage is:
Individual Day1 Day2 Day3 ... Day10
Actual Task: 0.7d 0.7d 0.7d ... 0.7d
Overhead : 0.3d 0.3d 0.3d ... 0.3d
But what I get is:
Individual Day1 Day2 Day3 ... Day10 Day11
Actual Task: 0.61d 0.7d 0.7d ... 0.7d 0.09d
Overhead : 0.26d 0.3d 0.3d ... 0.3d 0.04d
What I can't explain/fix is why Day1 is not fully
allocated. (Note: The individual is not assigned to
anything previous to this task). Anyone any ideas?
Thanks
Craig
I'm having the following problem with Project 2000. I
have a task that is say 7 days, which I assign an
individual to work. The individual is 70% efficient with
the remaining 30% as overhead. To represent this
I have:
Actual Task: 7 days work with assign Individual[70%]
giving 10 days duration
To make sure that the individual overhead is not
allocated elsewhere I create a second task for the
duration period i.e.
Overhead: 10 days duration Individual[30%]
What I expect to see in the resource usage is:
Individual Day1 Day2 Day3 ... Day10
Actual Task: 0.7d 0.7d 0.7d ... 0.7d
Overhead : 0.3d 0.3d 0.3d ... 0.3d
But what I get is:
Individual Day1 Day2 Day3 ... Day10 Day11
Actual Task: 0.61d 0.7d 0.7d ... 0.7d 0.09d
Overhead : 0.26d 0.3d 0.3d ... 0.3d 0.04d
What I can't explain/fix is why Day1 is not fully
allocated. (Note: The individual is not assigned to
anything previous to this task). Anyone any ideas?
Thanks
Craig