Resource Usage Report

E

essie88

i am trying to print the above report from a resource pool i have set up. it
will only show two days on the report? any suggestions?
 
J

JulieS

Hello essie88,

Open the pool file with the third option (Open resource pool read-write
and all other sharer files into a new master project file.) Then run
the Resource Usage Report from the master project file.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 