Resource Usage View

D

Debbie P

One of our users zeroed out all remaining work for a resource. When pulling
the field into the Resource Usage View however it still showed remaining
work. The resource in question did have Actual Work Protected for the same
amount of hours. When the Actual Work Protected field was inserted into the
view it shows 0.

It appears to me the data in the two fields are switched. Is this a known
issue or has anyone else noticed this problem? Is there a fix for it?

Thanks,

Debbie P
 
J

JulieS

Hi Debbie,

Are you using Project Server and Project Web Access (PWA)? Your reference
to "Actual Work Protected" leads me to believe you are. If so, I suggest
re-posting your question to the Project Server newsgroup as they may be able
to supply an answer more quickly.

I hope this helps.

Julie

Visit http://project.mvps.org/ for the FAQs and additional information about
Microsoft Project
 