%
% Complete vs Actual Work
Ok...I have a task that is 240 hours 41.16 days that is 95% complete....I
have two resources assigned to this task. I want them not to have a unit %
assigned to them...but everytime I get the hours and days adjusted the way I
want them it automatically makes the resource units for each resource to be
60%. Is there a way to not assign unit % to the resources?
Thank you!
have two resources assigned to this task. I want them not to have a unit %
assigned to them...but everytime I get the hours and days adjusted the way I
want them it automatically makes the resource units for each resource to be
60%. Is there a way to not assign unit % to the resources?
Thank you!