jojo
I allways have trouble with this and am hoping someone can help me.
if i have resource A and i schedule them to work 6 hrs a day on a project
that lasts 1 weeks. On the LAST day of the project my resource only needs
to work 4 hours i.e. my total work estimate was 20 hours. Does anyone know
how i can make it so that on the last day of the project, they are working
only 4 hrs.
i.e. from resource usage
1 2 3 4 5
resource A 6 6 6 6 6
i want it to be
1 2 3 4 5
resource A 6 6 6 6 4
I don't want it to be
1 2 3 4 5
resource A 5.2 5.2 5.2 5.2 5.2
thnaks
if i have resource A and i schedule them to work 6 hrs a day on a project
that lasts 1 weeks. On the LAST day of the project my resource only needs
to work 4 hours i.e. my total work estimate was 20 hours. Does anyone know
how i can make it so that on the last day of the project, they are working
only 4 hrs.
i.e. from resource usage
1 2 3 4 5
resource A 6 6 6 6 6
i want it to be
1 2 3 4 5
resource A 6 6 6 6 4
I don't want it to be
1 2 3 4 5
resource A 5.2 5.2 5.2 5.2 5.2
thnaks