resources group

M

milosnik.boczku

Hi there,

I am using MS Project 2003 and I wonder how can I create a "group of
resources" do automatize following case. Let's say, I've got 2
consultants and 4 tasks with different priorities. I don't care if
consulatant A will be assigned to task1, 2 or to 4. For me the most
important is that first available consultant (from my pool of 2 guys)
should be assigned to the task according to task and its priority.

Any idea? Plugins?

Regards,
MB
 
J

Jan De Messemaeker

Hi,

First, this unfortunately is not how Project works, is always asks for a
human intervention to assign a resource.
And unfortunately again, I do not know of any addin that does this.
It can be written but I do not know anybody who would have done it.

You can always ssign the task to "consultants" but then it will not be
assigned to one of them.
It's either or.

HTH
 