R
raydeo
If I have a resource that can work at 50% and I enter this in to the Max
Units for this resource, and then assign this resource to a task that should
last for 16 hours, shouldn't the number of days stretch to 4 from 2 if this
is the only resource assigned to this task? This is not the case that I am
running into. I did this and the resource was scheduled for 4 hours each day
(8 hour days), but the total hours remained at 16 hours. Has anyone else
experienced this? If any can shed some light on this issue I would greatly
appreciate it!!!
Units for this resource, and then assign this resource to a task that should
last for 16 hours, shouldn't the number of days stretch to 4 from 2 if this
is the only resource assigned to this task? This is not the case that I am
running into. I did this and the resource was scheduled for 4 hours each day
(8 hour days), but the total hours remained at 16 hours. Has anyone else
experienced this? If any can shed some light on this issue I would greatly
appreciate it!!!