Resources still red after leveling

V

Vic

Hi,

I'm trying to level someone else's existing plan and I'm doing it one
resource at a time so I can make assignment adjustments as needed. But for
some resources they get leveled but remain red. When I look at their tasks
that are red some are 8 hours or less (they are set for 8 hour work days).

Can anyone tell me why they remain red and how to solve that? Thanks in
advance for your help.
 
J

Jan De Messemaeker

Hi,

A resource is "red" when it is overallocated during a period of AT LEAST ONE
MINUTE.
So, when you have two meetings both scheduled 8-10, you may well only show 4
h of work that day but for Project you are overallocated - and in fact you
are unless you have the gift of bilocation.

If you want leveling to color all resources black you have to level "minute
by minute".

There's some more in FAQs 28 and 34 in
http://www.mvps.org/project/faqs.htm

HTH,


--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
V

Vic

Perfect! Thanks a lot!

--
Vic


Jan De Messemaeker said:
Hi,

A resource is "red" when it is overallocated during a period of AT LEAST ONE
MINUTE.
So, when you have two meetings both scheduled 8-10, you may well only show 4
h of work that day but for Project you are overallocated - and in fact you
are unless you have the gift of bilocation.

If you want leveling to color all resources black you have to level "minute
by minute".

There's some more in FAQs 28 and 34 in
http://www.mvps.org/project/faqs.htm

HTH,


--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 