I'm trying to level someone else's existing plan and I'm doing it one
resource at a time so I can make assignment adjustments as needed. But for
some resources they get leveled but remain red. When I look at their tasks
that are red some are 8 hours or less (they are set for 8 hour work days).
Can anyone tell me why they remain red and how to solve that? Thanks in
advance for your help.