Hi all together,
In MS Project I have a Resource where each you use it (type material) $
100.00 are billed. Now there are 13 pieces used in May. In the column
"Work" there stands correctly "13" and also the $100.00 appears in the
right column. BUT at the TimeScaleData the sum in May is only the value
of one piece ($100.00) and not the required 13*$100 = $1,300.00 ...
Does anybody knows why the sum won't be calculated the right way and
how to set it up?
Kind Regards,
Nachtigall
In MS Project I have a Resource where each you use it (type material) $
100.00 are billed. Now there are 13 pieces used in May. In the column
"Work" there stands correctly "13" and also the $100.00 appears in the
right column. BUT at the TimeScaleData the sum in May is only the value
of one piece ($100.00) and not the required 13*$100 = $1,300.00 ...
Does anybody knows why the sum won't be calculated the right way and
how to set it up?