D
dave sprinkle
I'm new to Project, so I'll concede this may be user error; however, it
appears that Project 2003 is incorrectly calculating task duration when I
change the units of one of my resources. An example:
1 -- Make a new task. Type is 'Fixed Work'. Assign 'resource 1' with 100%
utilization. Assign duration 100 hours.
2 -- Add 'resource 2' with 100% utilization. As you might expect, Project
recalculates duration to be 50 hours.
3 -- Reduce 'resource 2' utilization to 50%. In this case, Project
calculates duration to be 100 hours. Why? Our resource total is now 150% of
our nominal starting point, and yet Project is calculating 100% of our
nominal duration.
4 -- It gets worse. Reduce 'resource 2' utilization to 1%. In this case,
Project reports duration to be 5000 hours.
It seems Project is using the lowest utilization of the two resources and
applying that utilization to the entire effort. Where is the bug -- in
Project's calculation or in my understanding of Project's algorithm?
Thanks in advance for your assistance.
appears that Project 2003 is incorrectly calculating task duration when I
change the units of one of my resources. An example:
1 -- Make a new task. Type is 'Fixed Work'. Assign 'resource 1' with 100%
utilization. Assign duration 100 hours.
2 -- Add 'resource 2' with 100% utilization. As you might expect, Project
recalculates duration to be 50 hours.
3 -- Reduce 'resource 2' utilization to 50%. In this case, Project
calculates duration to be 100 hours. Why? Our resource total is now 150% of
our nominal starting point, and yet Project is calculating 100% of our
nominal duration.
4 -- It gets worse. Reduce 'resource 2' utilization to 1%. In this case,
Project reports duration to be 5000 hours.
It seems Project is using the lowest utilization of the two resources and
applying that utilization to the entire effort. Where is the bug -- in
Project's calculation or in my understanding of Project's algorithm?
Thanks in advance for your assistance.