N
newbold1
Is there a way to set it up in MS-Project for two
resources to be assigned to a task where they must work
together during the same hours?
For example, if I set-up an 8 hour task and assign two
resources, the program tries to split up the work. Also,
it allows each resource to work on the task as soon as
he/she is available.
What if I have a task that requires two resources with
different sets of expertise to work on the task together?
Let's say that John and Mary are working on a research
task and they need to work together because they both have
certain knowledge required to complete the task. If I
create the 8 hour task in MS-Project, it attempts to split
the work between them, effectively creating a 4 hour
duration. If John is busy with other tasks and Mary
isn't, MS-Project tries to get Mary started on the task
and adds John to it later. I found that I could set the
resources to 50% which causes the 8 hours of work to be
performed in an 8 hour duration. That's only part of the
fix. I still need to somehow cause their work scheduling
to be concurrent with each other for the full 8 hours of
work to be performed.
Any suggestions? Can it even be done?
Thanks!
resources to be assigned to a task where they must work
together during the same hours?
For example, if I set-up an 8 hour task and assign two
resources, the program tries to split up the work. Also,
it allows each resource to work on the task as soon as
he/she is available.
What if I have a task that requires two resources with
different sets of expertise to work on the task together?
Let's say that John and Mary are working on a research
task and they need to work together because they both have
certain knowledge required to complete the task. If I
create the 8 hour task in MS-Project, it attempts to split
the work between them, effectively creating a 4 hour
duration. If John is busy with other tasks and Mary
isn't, MS-Project tries to get Mary started on the task
and adds John to it later. I found that I could set the
resources to 50% which causes the 8 hours of work to be
performed in an 8 hour duration. That's only part of the
fix. I still need to somehow cause their work scheduling
to be concurrent with each other for the full 8 hours of
work to be performed.
Any suggestions? Can it even be done?
Thanks!