resources time commitments on a schedule

J

JayC

After I have all my resources allocated to their respective tasks, I would
like to see a quick snapshot of the requirements of a specific resource. So I
can leave a one page document showing the resource where they have been
allocated for the nest time frame. It would also be usefull in planning which
resource to use for future tasks.
 
J

Jan De Messemaeker

Hi JayC,
Look at the Resource Usage View whichyou can filter on any one resource.
HTH
 