J
jackvinson
Dumb question time, as I am sure this is answered somewhere. I don't know
the proper lingo to find what I need. I'd appreciate advice on where I can
read more or see examples for this one.
The primary question: How do I deal with resources that have multiple
calendars, such as people and equipment.
I have people and equipment. The equipment may run 24-hours, so I've given
them the 24-hour calendar. People only work on the calendar that I've set
for the project (slight modifiocation of the Standard calendar).
When I assign a task to a piece of equipment, it will not run at night.
There are no people associated with the task.
I'm even more confused when I have a task assigned to both humans and
equipment that splits over a day.
[And why do the task durations keep changing when I change calendars or add
resources? I've set them all to Fixed Duration. Do I need to turn off
"effort driven" as well?]
the proper lingo to find what I need. I'd appreciate advice on where I can
read more or see examples for this one.
The primary question: How do I deal with resources that have multiple
calendars, such as people and equipment.
I have people and equipment. The equipment may run 24-hours, so I've given
them the 24-hour calendar. People only work on the calendar that I've set
for the project (slight modifiocation of the Standard calendar).
When I assign a task to a piece of equipment, it will not run at night.
There are no people associated with the task.
I'm even more confused when I have a task assigned to both humans and
equipment that splits over a day.
[And why do the task durations keep changing when I change calendars or add
resources? I've set them all to Fixed Duration. Do I need to turn off
"effort driven" as well?]