Udderjuice said:
Hello, I have rolled up certain sub-tasks and milestones to the summary bar
but when I hide the sub-tasks they don't show up any more. I want to be able
to print a sheet that only shows the summary bar for each of my projects but
also displays the rolled up information but can not get it to do this.
Thanks.
Udderjuice,
If I take your first sentence literally, why would you expect the
sub-tasks to show if they are hidden? However, I will assume you mean
that the rolled up subtasks DO show on the summary line but only if the
summary is expanded (i.e. subtasks visible).
Three things control whether subtask bars show up at summary level.
First, each of the subtasks must be set to roll up to summary level
(Project/Task Information/General tab). Second, the summary line must
also be set to show rolled up Gantt bars (Project/Task
Information/General tab). Third, there must be a bar style for normal,
rolled up, not summary (Format/Bar Styles/Show For...Tasks column).
Given those settings, subtask bars will display on the summary line
whether subtasks are collapsed or expanded.
If you have all of the above things set and it still isn't working, then
I suspect either the file is corrupt or something in the Bar Styles
format is blocking the bars although I can't replicate a configuration
that would react that way. If you suspect file corruption, does this
occur will all files or just one file? If it is just the one file, go to
our MVP website at:
http://project.mvps.org/faqs.htm
and take a look at FAQ 43 - File Bloat? Might be corruption.