running a date range filter on Actual Work

E

Eric H

how do you do run a filter that shows the Actual Work done in a certain
date range and not the total Actual Work done?
 
R

Rod Gill

Select View, Task Usage or Resource Usage.
Right-Mouse click the yellow area and select Actual Work.

Now you can see Actual work by any time frame you want: edit the timescale
to suit.
 
E

Eric H

Thanks again Gill for the help. I checked it out --now is there a way under
Resource Usage to see the tasks for each Resource not left aligned but still
in outline view of the Gantt Chart? Otherwise its very hard to read what
happened by that resource on that particular day. Is there a way to make a
pretty report from that information to show to boss and client? Thanks
again.
 