When mapping Task Data, I select Assignment Units. This field is selected but
the pivot table column is blank !

Any idea why it's not populated? I am using a custom map.

MSPLearner
 
J

JulieS

Hi MSPLearner

From Help on the Assignment Units field (task field):
=========================
Entry Type: Null

Best Uses: Add the Assignment Units field to the Task Usage view when you
want to display the allocation of time for each individual assignment. No
information is displayed in the Assignment Units task field; it merely makes
the corresponding Assignment Units field for the assignments available.

====================================

If you attempt to add the Assignment Units field to a task table, you will
see it is empty (Null as noted in Help.). The Assignment units field is
designed for the Task Usage view.


I hope this helps. Let us know how you get along.


Julie

Visit http://project.mvps.org/ for the FAQs and additional information about
Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top