From Help on the Assignment Units field (task field):
=========================
Entry Type: Null
Best Uses: Add the Assignment Units field to the Task Usage view when you
want to display the allocation of time for each individual assignment. No
information is displayed in the Assignment Units task field; it merely makes
the corresponding Assignment Units field for the assignments available.
====================================
If you attempt to add the Assignment Units field to a task table, you will
see it is empty (Null as noted in Help.). The Assignment units field is
designed for the Task Usage view.
I hope this helps. Let us know how you get along.
Julie