Saving a baseline
I just want to confirm something. If I baseline an entire plan and track
progress for a week, then add a few new task items. When I save the baseline
again, I only save the selected task (the new ones) using the option in to
only save the selected task, this will not re-set the baseline for the entire
project tight? It will only add the new selected task to the existing
baseline right?