L
LeslieF
Hello,
As many have been reading, I have a master project file with many (~30)
inserted files. Some of these sub-project files have been created with a
"schedule from Project Finish Date", although most are scheduled from project
start date. The master project file is scheduled from project start date
(which is 1/7/05).
However, greyed out in the "finish date" box of the master file is a date of
6/23/05.
My dilemna is that when I open the master project, those files that are
scheduled from project finish date show a "finish" date of 6/23 (which is
incorrect) but when I expand to show all the projects tasks, the "finish"
date reverts to the true project finish date.
Is this a bug or can someone help me to understand the behavior? At the
moment, the users of the master file have to "show all subtasks" then "show
outline level 1" to see an accurate finish date in the master project.
Another way to ensure that the master file user can see the accurate date is
to be sure the subprojects are open, though this seems to defeat the purpose
of wanting to work in a single file!
Any advice or suggestions someone can give me would be really great!
....L
As many have been reading, I have a master project file with many (~30)
inserted files. Some of these sub-project files have been created with a
"schedule from Project Finish Date", although most are scheduled from project
start date. The master project file is scheduled from project start date
(which is 1/7/05).
However, greyed out in the "finish date" box of the master file is a date of
6/23/05.
My dilemna is that when I open the master project, those files that are
scheduled from project finish date show a "finish" date of 6/23 (which is
incorrect) but when I expand to show all the projects tasks, the "finish"
date reverts to the true project finish date.
Is this a bug or can someone help me to understand the behavior? At the
moment, the users of the master file have to "show all subtasks" then "show
outline level 1" to see an accurate finish date in the master project.
Another way to ensure that the master file user can see the accurate date is
to be sure the subprojects are open, though this seems to defeat the purpose
of wanting to work in a single file!
Any advice or suggestions someone can give me would be really great!
....L