schedule is altered when imported to master schedule. The date cha

D

debbie

when i import a project that is created by a team member the schedule shows
with different dates then the on they created.
 
H

Hisham

hi debbie:

- Which version you are using for MSP?
- What is the calendar used with the impoted project and what is the
calendar in the master project? are they the same?
- Have you checked the options (tools -> options -> calendar) & (tools ->
options - schedule) are you using the same setting at both the imported and
the master projects?

Let us know how you get along.

BR
Hisham
http://epmforum.wordpress.com
 