Schedule revision control

T

Troy Lee

I searched and really couldn't find an answer to my question. How do
you handle revision control on the schedules? Is there a way to insert
a field and update it and have it print out in the legend or footer?

Troy
 
M

Mike Glen

Hi Troy,

Welcome to this Microsoft Project newsgroup :)

You can use any of the free fields: eg Text1 or Date1, to insert the date a
task was updated, if that's what you're after. You can then select that
field in either the Legend or Header, whatever you wish. But why not insert
the revision date directly?

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top