schedule slips

P

Peggy

Someone has asked me to show that a group of tasks has slipped two weeks. I'm
not sure how, or if, I can do this. Can you please help?
 
M

Mike Glen

Hi Peggy,

Welcome to this Microsoft Project newsgroup :)

Try View/Tracking Gantt. You must have saved the baseline first though, as
the Tracking Gantt shows the original baselined plan against the current
plan.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))