Schedule with fixed work and fixed duration

R

rdtraversi

I would like to schedule a project with a fixed number of hours (work?) and a
fixed duration for each task.

I tried to do resource levelling to get a new schedule based on the hours,
duration, and resources but I get messages saying that tasks cannot be moved.
I made sure all my constraints are ASAP.

Any suggestions?

Thank You.
 
R

Rod Gill

So what has to give is the hours per week each resource has to work. Project
does not change units when levelling at all so if you need more units than
you have available to do the work in the duration you specify, it's your
problem to resolve!

--

Rod Gill
Project MVP

NEW!! Project VBA Book, for details visit: http://www.projectvbabook.com
 
M

Mike Glen

Hi rdtraversi ,

Welcome to this Microsoft Project newsgroup :)

Have any of the tasks got actual work entered or given an actual start date
or % complete?
Are you scheduling from the finish?

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top