scheduled work till the status date

H

Hans Wurst

Hey there!

In our status reports we have the scheduled work till the status date.
Is there I field where I can see that value (days, not cost)?

Now I need to to have a look at the timephased data and add all the values :-(

Kind regards

Michael
 
J

JulieS

Hi Michael,

In the Resource Usage or Task Usage view you could add the Cumulative Work
field to show how much work has been schedule as of a specific day.

I hope this helps. Let us know how you get along.
Julie
 