Hi All:
Can you please help me address this situation?
On a project with only 4 tasks, I want 10 resources to have 5% of their
daily activity scheduled across the year. The 5% should never change as a
resource allocation but there actual numbers can be less then or greater than
the 5%. The start and finish date are the same for each task.
When their actual work is applied, it changes their Units (which I believe
is Peak alloc). Some resources have Units showing up as greater than 5%, what
worries me is that it is changing the work distributed on resources.
What is causing this to change the 5% alloc on the remainder of days. My
task settings are
Fixed Units
Finish No Earlier than (Finish date)
Effort Driven is unchecked.
Estimated? box is checked.
Any help on how to handle the issue is appreciated.
Thanks.
Can you please help me address this situation?
On a project with only 4 tasks, I want 10 resources to have 5% of their
daily activity scheduled across the year. The 5% should never change as a
resource allocation but there actual numbers can be less then or greater than
the 5%. The start and finish date are the same for each task.
When their actual work is applied, it changes their Units (which I believe
is Peak alloc). Some resources have Units showing up as greater than 5%, what
worries me is that it is changing the work distributed on resources.
What is causing this to change the 5% alloc on the remainder of days. My
task settings are
Fixed Units
Finish No Earlier than (Finish date)
Effort Driven is unchecked.
Estimated? box is checked.
Any help on how to handle the issue is appreciated.
Thanks.