C
Chris W
Hello,
We have a situation where a fixed unit task that will take 11.2 hours in
total is 44% complete (rem work = 7.2, duration = 18.29, utilisation @ 70%)
At this point the project was rescheduled and levelled which resulted in the
task being split and the remaining work resuming 10 days later.
We tried increasing the task priority to be the highest in the project and
re-levelling however this does not bring the task in. Checking resource
usage, the task itself shows 0 hours on each day until the 1st of May.
We can manually bring this in by dragging the task itself however id like to
follow the logic which is making Project calculate these dates. Any help will
be appreciated.
We have a situation where a fixed unit task that will take 11.2 hours in
total is 44% complete (rem work = 7.2, duration = 18.29, utilisation @ 70%)
At this point the project was rescheduled and levelled which resulted in the
task being split and the remaining work resuming 10 days later.
We tried increasing the task priority to be the highest in the project and
re-levelling however this does not bring the task in. Checking resource
usage, the task itself shows 0 hours on each day until the 1st of May.
We can manually bring this in by dragging the task itself however id like to
follow the logic which is making Project calculate these dates. Any help will
be appreciated.