lilfos
Hi,
I'm using Project 2003 to estimate where milestones will fall for a
1.5-person effort. Each resource has their own schedule. One works 4
days per week, the other works 1 day per week. I assigned the 4-day
resource to all tasks initially. I would like to add the 1-day
resource to certain tasks and see the duration for those tasks shorten
due to the extra help.
Instead, what I am seeing is that the task is split until the 1-day
resource is on duty. Project assumes that the 2nd resource is
required, whereas I want them to be optional and to help out with tasks
that fall on their work day. With the split, the 4-day resource is
twiddling his thumbs for 3 days.
All tasks are fixed work and effort-driven. The schedule currently
shows how long it will take with just the 4-day resource.
Anyone know how I can make the schedule shorten as a result of letting
the 1-day resource help out on certain tasks?
Thanks!
I'm using Project 2003 to estimate where milestones will fall for a
1.5-person effort. Each resource has their own schedule. One works 4
days per week, the other works 1 day per week. I assigned the 4-day
resource to all tasks initially. I would like to add the 1-day
resource to certain tasks and see the duration for those tasks shorten
due to the extra help.
Instead, what I am seeing is that the task is split until the 1-day
resource is on duty. Project assumes that the 2nd resource is
required, whereas I want them to be optional and to help out with tasks
that fall on their work day. With the split, the 4-day resource is
twiddling his thumbs for 3 days.
All tasks are fixed work and effort-driven. The schedule currently
shows how long it will take with just the 4-day resource.
Anyone know how I can make the schedule shorten as a result of letting
the 1-day resource help out on certain tasks?
Thanks!